THE LEGEND CITY DA NANG COMPLETES MASSIVE TRANSFER SLAB AND BEAM CONCRETE POUR

From the evening of August 4 to the early morning of August 5, 2026, the CENTRAL’s PMB at The Legend City Da Nang successfully completed the concrete pouring for the Level 4 transfer slab and beams, featuring a structural depth of 2.7 meters and a width of 2.95 meters. The milestone is recognized as the largest transfer slab and beam system completed in Da Nang to date, marking a significant achievement in the project’s construction progress.

The large-scale concrete pour involved approximately 4,500 m³ of mass chilled concrete, 1,000 tons of reinforcement steel, and an integrated post-tensioning cable system within the transfer beam structure. The substantial material volume and stringent technical requirements demanded meticulous planning, coordination, and quality control throughout every stage of execution.

To ensure uninterrupted construction, the PMB worked closely with multiple major concrete suppliers, mobilizing dozens of concrete mixer trucks, boom pumps, and line pumps to operate continuously overnight and maintain a stable concrete supply throughout the pour.

Strategically located on a prime site with four frontages at the foot of Cau Rong Bridge, The Legend City Da Nang comprises 03 basement levels and two 29-story towers, accommodating hotel and high-end residential functions. The project is currently among the prominent developments attracting significant attention in Da Nang and the Central Vietnam’s real estate market.

As the final concrete pumping operations were completed, a strong sense of pride was evident among the engineers and workers on site. The successful pour was not only the result of many hours of continuous effort, but also a testament to the close coordination, strong sense of responsibility, and determination demonstrated by the Client, CENTRAL, and all partners.

Following this major milestone, the PMB will continue executing the structural works for the typical floors, steadily advancing the project in line with the committed schedule and quality standards.

Congratulations to the entire The Legend City Da Nang’s PMB!

NGUYEN TAT THANH BRIDGE PROJECT COMMENCES INSTALLATION OF THE FIRST SUPER-T GIRDERS

Just over four months after taking possession of the construction site, the Nguyen Tat Thanh Bridge Project in Cam Lam Commune, Khanh Hoa Province has successfully launched the installation of its first Super-T girders, marking a significant milestone in the bridge’s structural construction. In parallel, pier construction and girder casting activities continue as planned to maintain the project’s overall schedule.

Spanning approximately 800 metres across the Thuy Trieu Lagoon on Nguyen Tat Thanh Boulevard, the bridge is designed with a modern steel arch structure integrated with reinforced concrete, featuring two independent spans to ensure long-term structural integrity, operational safety, and durability. As a key transportation infrastructure project, the bridge will strengthen connectivity between Nha Trang City, Cam Lam, and Cam Ranh International Airport, while contributing to the completion of the regional transport network and supporting the socio-economic development of southern Khanh Hoa Province.

Project Site Overview of the Nguyen Tat Thanh Bridge Project, Cam Lam Commune, Khanh Hoa Province

According to the construction schedule, the installation of all Super-T girders is expected to be completed by September this year. Demonstrating strong commitment and determination, CENTRAL’s PMB, together with its engineers, technical staff, and construction workforce, is accelerating site activities around the clock by mobilising maximum manpower and equipment to ensure the project is delivered on schedule, while meeting the highest standards of quality, safety, and technical excellence.