NGUYEN TAT THANH BRIDGE PROJECT COMMENCES INSTALLATION OF THE FIRST SUPER-T GIRDERS

Just over four months after taking possession of the construction site, the Nguyen Tat Thanh Bridge Project in Cam Lam Commune, Khanh Hoa Province has successfully launched the installation of its first Super-T girders, marking a significant milestone in the bridge’s structural construction. In parallel, pier construction and girder casting activities continue as planned to maintain the project’s overall schedule.

Spanning approximately 800 metres across the Thuy Trieu Lagoon on Nguyen Tat Thanh Boulevard, the bridge is designed with a modern steel arch structure integrated with reinforced concrete, featuring two independent spans to ensure long-term structural integrity, operational safety, and durability. As a key transportation infrastructure project, the bridge will strengthen connectivity between Nha Trang City, Cam Lam, and Cam Ranh International Airport, while contributing to the completion of the regional transport network and supporting the socio-economic development of southern Khanh Hoa Province.

Project Site Overview of the Nguyen Tat Thanh Bridge Project, Cam Lam Commune, Khanh Hoa Province

According to the construction schedule, the installation of all Super-T girders is expected to be completed by September this year. Demonstrating strong commitment and determination, CENTRAL’s PMB, together with its engineers, technical staff, and construction workforce, is accelerating site activities around the clock by mobilising maximum manpower and equipment to ensure the project is delivered on schedule, while meeting the highest standards of quality, safety, and technical excellence.

  • Youtube: https://youtu.be/Vt3hREz4vVk

Highlights photos of the Super-T girder installation:

Post related