THE COMMENCEMENT CEREMONY OF “SALE GALLERY THE ESTUARY”, TRADE CENTER & LUXURY APARTMENT TUYEN SON – DA NANG PROJECT

On the morning of December 3, 2019, CENTRAL and Tuyen Son Housing development Co.., LTD Investor was held the commencement ceremony “Sale Gallery the Estuary” – Trade Center & Luxury apartment Tuyen Son project at Hai Chau District, Da Nang City.

Perspective of Trade Center & Luxury apartment Tuyen Son – Da Nang project

The ceremony honored to have the presence of guests, icluding:

  • As Investor:
    • Mr. Nguyen Anh Tuan – CEO
    • Mr. Do Hai Minh – D.CEO
  • As CENTRAL:
    • Mr. Mai Chanh Thanh – Executive Director
    • Mr. Vo Quang Dat – Site Manager
    • Mr. Tran Dinh Vy – Site Manager MEP

And the staff of 2 companies

Mr. Nguyen Anh Tuan & Mr. Mai Chanh Thanh making an incense offering with SMB

Trade Center & Luxury apartment Tuyen Son project has been built in an area of 1,8ha, located conveniently at Tien Son bridge, the center of Da Nang, opposite of Lotte Mart, with 2 blocks, 2 basements, and 40 floors. The total investment is up to 2.300 billion VND

Sale Gallery The Estuary Tuyen Son

After the construction test pile, SMB is ready for the initiation of construction. The commencement ceremony “Sale Gallery the Estuary” The model construction helps investors’ marketing and sales in the future.

Real construction photo test pile.

CENTRAL plays a role as a general contractor in D&B. The progress chart is 26 months and the handover time is in January 2020.

Real construction photo of the project

This project is also a pride of the engineering team, CENTRAL’s engineers have a high determination for building an amazing, beautiful design, offering the best solutions for customers

A take photo BOD of Tuyen Son & CENTRAL

The event commencement ceremony “Sale Gallery the Estuary” will be an initial step of building a Trade Center & Luxury apartment Tuyen Son project. It also represents a CENTRAL big project in Da Nang, a city of light of Vietnam

Some pictures of the ceremony:

THE TOPPING CEREMONY OF THE TALLEST BUILDING OF PHASE 1 – VINHOMES GRAND PARK

The topping ceremony of L16 – the tallest of Phase 1, Vinhomes Grand Park has been held on the morning of November 29th, 2019, district 9, HCMC.

The ceremony was honored to welcome

  • From Investors – VINGROUP
    • Mr. Trinh Chi Cong – Project Director
    • Mr. Nguyen Duc Tu – Safety Manager
    • Mr. Ho Cong Phuc – Consultants Manager
  • From Contractor CENTRAL
    • Mr. Pham Van Hung – Project Director
    • Mr. Vo Minh Thanh, Mr. Duong Hong Cong, Mr. Nguyen Dinh Le, Mr. Vu Ba Cuong – Site Manager  in common with supplier, Subcontractors and SMB project
Mr. Trinh Chi Cong and SMB project making an incense offerings
The representation Investor and SMB is making the releasing balloons ceremony

L16 in Phase I, with 35 floors and 2 basements. CENTRAL plays a role as the General Contractor in structure, completion, and MEP. Currently, CENTRAL is constructing 8 towers in the Vinhomes Grand Park project at the same time.

Real constructions Phase 1 – Vinhomes Grand Park project

L16 was the latest tower handover by pile contractor in Phase 1, but its construction speed is ahead of the scheduled 50 days. This has been gained the investor’s highest appreciation in professionalism and considerable effort of a whole SMB.

Real construction of L16- the tallest building of Phase I – Vinhomes Grand Park
Image of installing MEP system at the corridor
Use precast wall panel
Execution of M&E system as soon as the N-4 formwork has been removed
M&E system follows the structure floor
The photo of finishing work and typical M&E work in the corridor
The photo of finishing work and typical M&E work inside the apartment

After the topping ceremony, SMH continued to urgently implement the finishing work and another field for the safest and highest quality project. The estimated time of L16 is in July 2020.

Some pictures of the ceremony:

CENTRAL’s REPEATED WINNING PROJECTS IN NOVEMBER

In November 2019, CENTRAL has repeatedly received 3 projects winning with a total value of approximately 1 billion VND. Then, BOD of CENTRAL along with project leaders, proceed construction to timely meet the deadline for Investor.

2/ LUXURY APARTMENT AND SAIGON ASIANA TRADE IN SERVICES Project

Located conveniently at the administrative center in district 6 (Hau Giang – Nguyen Van Luong street), there is a heart of bustling Sai Gon Cho Lon trade market. Luxury apartments and Saigon Asiana Trade in Services invested wholeheartedly by Gotec Vietnam have a good chance to offer high quality and unique products to the market.

The project with 2 basements, 16 floors. The standing point of Saigon Asiana is the multi-functional garden at the rooftop including Sinh Khi garden, Thien Yen garden, Nang Luong garden, and Yen Tiec garden.

Perspectives SAIGON ASIANA project

In this project, CENTRAL has gained Investor trust and been appointed as a General contractor in structure, complete, and MEP. Before that, BOD along with the engineering team has offered some best solutions in technical and aesthetically estimated design and helps Investors save expenses as much as possible.

Gotec Viet Nam is known for Asiana restaurant chains such as Binh Thanh Asiana Plaza, Asiana Capella, Tan Phu Asiana Plaza.

2/ GRAND BAY HA LONG Project

Ha Long Grand Bay is a project belonging to 3 peninsulas of Ha Long Marina (Hoang Quoc Viet street, Bai Chay) of BIM Group – a well-known real estate.

At the beginning of 2019, CENTRAL and BIM Group collaborated in SYRENA APARTMENT AND HOTEL (Tay Ho, Ha Noi), this project is the first step of both sides’ cooperation.

In November 2019, CENTRAL has won a structural construction and civil work for 106 shophouses and 61 villas. With much experience in Shophouse and Villas, Grand Bay Ha Long will surely have excellent aesthetics when hanging over.

Perspectives of Grand Bay Ha Long

Ha Long City is a new city with much potential development in the economy and society of Quang Ninh province, the real estate hype here isn’t still cool yet. And Grand Bay Ha Long would be the one that boosts and define CENTRAL’s reputation to Investor here.

3/ CMC CREATIVE SPACE Project

CMC Creative Space is an office complex and data center in the South of CMC Tech Group of Investor located at Tan Thuan Export Processing Zone, District 7, HCMC.

Perspective of CMC Creative Space project

Built-in 13000m2 total area, CMC Creative Space consists of a data building center between 2 offices. In this project, CENTRAL won a construction of tunnel basement, body, and finishing work for 3 main blocks (Block A, Block B, Block DC) and some other buildings.

CENTRAL with many remarkable experiences in large-scale building projects such as Etown 5, UOA, MWG. Besides, high technology, as well as experienced engineers, gain Investor trust in deadline commitment, quality, and aesthetics.

THE TOPPING OUT CEREMONY OF VINHOMES GRAND PARK PHASE 1– L15

On the morning of November 11, 2019, CENTRAL & VINGROUP organized the Topping Out Ceremony of VINHOMES GRAND PARK PHASE 1 – L15 at District 9, HCMC.

The ceremony was honored to welcome

  • From Investors – VINGROUP
    • Mr. Trinh Chi Cong – Project Director
    • Mr. Nguyen Anh Tuan; Mr. Nguyen Phi Nam – Consultants Manager
  • From Contractor CENTRAL
    • Mr. Vu Ba Cuong, Mr. Duong Hong Cong, Mr. Vo Minh Thanh, Mr. Nguyen Dinh Le – Site Manager in common with supplier, Sub-contractors, and SMB project
Mr. Trinh Chi Cong and SMB project making an incense offerings

At the project, CENTRAL is a general contractor for 8 Towers. The contractor uses the new construction method – FULL TOP DOWN – building a basement and the body at the same time

Perspective of Vinhomes Grand Park

L15 is 2 basements located in phase 1. CENTRAL acts as General Contractor for construction finishing structure and MEP. SMB has exceeded the Toping out before 1 month as required schedule from the Investor

Real construction photo at L15
Image of installing MEP system of apartment
Image of the concrete surface after striking formwork
Image of installing precast wall panel
Image of finishing work.

This ceremony was a warm, cheerful atmosphere. Immediately after the Topping Out ceremony, SMB L15 continued to urgently implement the finishing work, satisfying the requirements of the Investor.

THE TOPPING OUT CEREMONY OF VINHOMES GRAND PARK PHASE 1– L17

On the morning of October 10, 2019, CENTRAL & VINGROUP organized the Topping Out Ceremony of VINHOMES GRAND PARK PHASE 1 – L17 at District 9, HCMC.

The ceremony was honored to welcome:

  • From Investors – VINGROUP
    • Mr. Nguyen Duc Quang – Executive Director
    • Mr. Trinh Chi Cong – Project Director
    • Mr. Nguyen Anh Tuan – Consultants Manager
    • Mr. Nguyen Duc Tu – Project Security Manager
  • From Contractor – CENTRAL
    • Mr. Mai Chanh Thanh – Executive Director
    • Mr. Pham Van Hung – Project Director
    • Mr. Vo Minh Thanh, Mr. Vu Ba Cuong, Mr. Duong Hong Cong – Site Manager in common with supplier, Subcontractors, and SMB project


Mr. Nguyen Duc Quang, Mr. Mai Chanh Thanh, and SMB project making incense offerings

At the project, CENTRAL is a general contractor for 8 Towers. The contractor uses the new construction method – FULL TOP DOWN – building a basement and the body at the same time

L17 is 2 basements located in phase 1. CENTRAL has handed over the construction site later than other units about 1 month in the whole project but up to now, the project has topped off 1 month ahead of the investor’s request.

It is expected that the L17 will be the earliest one to be handed over to investors among all the towers in phase 1 in April 2020.


Perspective of Vinhomes Grand Park Phase 1 – L17


Real construction photo at the project


Cast-in-situ concrete: beam, slab, ceiling, column, shear wall
Image of the concrete surface after striking formwork


Image of installing precast wall panel


Image of installing MEP system of apartment


Image of installing MEP system at the corridor


Image of finishing work of typical WC

Immediately after the Topping Out ceremony, SMB continued to urgently implement the finishing work, meeting all safety and quality standards, satisfying the requirements of the investor.

Some pictures of the ceremony:

THE TOPPING OUT CEREMONY EVASON ANA MANDARA I&II ANA MANDARA I&II COMPLEX PROJECT

On the morning of September 17, 2019, CENTRAL & Investor Sovico Khanh Hoa Co. Ltd organized the Topping Out Ceremony of Evason Ana Mandara I&II – Ana Mandara Complex, Cam Ranh.

The ceremony was honored to welcome The Investor: Mr. Luu Van Son – Chairman of the Members’ Council Sovico; Mrs. Nguyen Thi Thu Nguyet – CEO of Sovico. Contractor representative – Mr. Cao Son Hung – Project Director; Mr. Pham Chi Hieu – Site Manager in common with Design consultant, Subcontractors and SMB project.

Mr. Cao Son Hung with SMB is making topping out ceremony

The project is built on an area of 48.000m2, Ana Mandara I&II include 2 hotel, each hotel has 8 floors and 1.300m2 for each floor. CENTRAL plays a role contractor: structure and rough finishing. The estimated to complete for hand over about the end of 2019.

Raising the golden bar

The Ana Mandara complex with architecture bold Vietnamese conical. Therefore, the entire structure around the outside of the 2 hotels is curved, winding, creating unity with the whole area. Besides, the space used for each hotel floor is different. For the 6th floor, designed 4 rooms including 4 villa sea view swimming pool (230m2). The project promises to bring guests a unique space and a resort stay that is peaceful, relaxed.

Perspective Evason Ana Mandara I&II project

Some pictures of the ceremony: