CENTRAL UPDATES CONSTRUCTION PROGRESS OF MASTERI RIVERA DANANG PROJECT

Following three months since the topping-out milestone on December 2, 2025, the Masteri Rivera Danang project, developed by Masterise Homes with CENTRAL Construction Joint Stock Company serving as the Design & Build General Contractor, has entered the final stage of completion. Construction progress is being accelerated to ensure readiness for handover, scheduled for the end of July 2026.

Strategically located in Hoa Cuong Ward, Masteri Rivera Danang benefits from strong connectivity and significant development potential. It comprises two basements and two towers rising 40 floors, built on a 1.82-hectare site, with a total CFA of 165,595 square meters. In its role as D&B General Contractor, CENTRAL has been working closely with the developer and Vertical Studio to deliver the project in accordance with stringent technical and quality standards, aiming to create a modern and sustainable architectural landmark in Da Nang.

Actual images of Masteri Rivera Danang

Recently, the CENTRAL’s PMB successfully completed the energization and commissioning phase of the MEP system. In parallel, efforts are being focused on interior finishing works, including installation of fixtures and fittings within the apartments, as well as façade completion and landscape development.

The MEP process has been executed under a strictly controlled framework, with close coordination among CENTRAL’s PMB, the investor, supervision consultants, and subcontractors. Each component has undergone systematic inspection, calibration, and phased acceptance to ensure operational safety, system stability, and long-term performance. This milestone not only marks the technical completion of critical systems but also validates the project’s readiness for operational use.

Công tác đóng điện được triển khai và kiểm soát chặt chẽ bởi BCH CENTRAL và các đơn vị thi công dự án

The acceleration of finishing works reflects the strong commitment and coordinated efforts of all parties involved. This phase demands a high level of precision, strict quality control, and disciplined execution to ensure that every detail meets the highest standards prior to handover. It also serves as a clear testament to CENTRAL’s capability in delivering large-scale, complex projects that meet increasingly rigorous technical and quality requirements.

Wishing the CENTRAL’s PMB is on track to successfully complete and hand over the project as planned!

A preview of the refined and upscale living environment envisioned at Masteri Rivera Danang in the near future:

CENTRAL UPDATES CONSTRUCTION PROGRESS OF MIDORI THE NEST PROJECT BY BECAMEX TOKYU (JAPAN)

Recently, the investor consortium Becamex Tokyu (Japan) officially announced the launch plan for Midori The Nest, located in the Science and Technology Urban Area in Northern Ho Chi Minh City. This is a distinctive apartment project targeting the young generation segment and is being constructed by CENTRAL Construction Joint Stock Company as the general contractor.

Actual site images of Midori The Nest project at present

Becamex Tokyu is a joint venture between Tokyu Corporation (Japan) and Becamex IDC (Vietnam), established with the vision of developing urban areas in Binh Duong New City (1,000 hectares), including residential, commercial, and transportation complexes within the integrated “TOKYU Garden City.” In alignment with the investor Becamex Tokyu’s philosophy of creating refined, high-quality, and healthy living environments, CENTRAL focuses on delivering excellence in every construction activity, maintaining the value standards set by the investor through the capabilities of a leading construction contractor in Vietnam.

At Midori The Nest, CENTRAL undertakes the role of general contractor for a development comprising two 25-storey towers, expected to offer apartment units ranging from 35 to 117 sqm, featuring optimized layouts and integrated amenities that meet the living, working, and recreational needs of young residents.

According to the latest update from the project management team: Tower H7 has reached the structural stage of Level 4 Floor; Tower H5 has reached the structural stage of Level 3 Floor. All construction areas are arranged in an open and organized manner to ensure construction quality

Logistics preparation phase of Midori The Nest project

From the early stages of project implementation, preparatory works such as site logistics planning, mobilization of manpower and equipment, and deployment of safety measures were carried out promptly and systematically, meeting stringent Japanese standards. With quality and efficiency as guiding principles, CENTRAL proactively allocates resources, leverages its deep construction expertise, and combines local site understanding to implement optimal technical solutions for each work package. The entire construction process is strictly controlled through a rigorous quality management system to ensure compliance with high technical standards while maintaining efficient project progress.

Well-organized and tidy construction site layout

Beyond maintaining a well-organized construction site, CENTRAL also ensures that the project management office is arranged scientifically. All workspaces follow strict organizational standards, ensuring cleanliness and order, while documentation is systematically managed and properly stored to optimize retrieval efficiency, save time, and enhance overall productivity.

CENTRAL project site office arranged in a structured and professional manner

The introduction of Midori The Nest is expected to contribute meaningfully to addressing urban housing challenges in a practical and human-centered approach, while laying the foundation for a modern and sustainable living model for future generations. With strict acceptance requirements from the Japanese investor Becamex Tokyu and the supervision consultant Bureau Veritas, CENTRAL’s PMB is committed to achieving the shared goal of delivering the project in line with safety – quality – schedule – efficiency, meeting all expectations from the developer.

Participation in the project is also a source of pride for CENTRAL, as it continues to partner with Becamex Tokyu in creating a distinctive development where construction quality is harmoniously integrated with refined architectural language. Beyond affirming CENTRAL’s capabilities, the project also contributes to enhancing the position of Vietnam’s construction industry through internationally standardized developments.

GROUNDBREAKING CEREMONY OF OASIA SWANBAY VILLAS PROJECT – SUMI & MIYABI SUB-ZONES

On the morning of March 17, 2026, CENTRAL Construction Joint Stock Company in collaboration with the developer Dai Phuoc Swancity One Mea, held the groundbreaking ceremony for the Oasia SwanBay Villas Project – Sumi & Miyabi Sub-zones, located within the SwanBay urban area on Dai Phuoc Island, east of Ho Chi Minh City.

The ceremony was attended by representatives of the Developer, supervision consultant, CENTRAL’s PMB, along with partners, subcontractors, and construction crews.

Representatives of all parties perform the groundbreaking ceremony of the project

Surrounded by the Saigon River on all sides, the Oasia SwanBay Villas Project – Sumi & Miyabi sub-zones are considered the “final piece” in shaping the premium SwanBay urban development. Strategically positioned at the eastern gateway of Ho Chi Minh City, adjacent to former District 2 and District 9, the project benefits from strong connectivity to Long Thanh International Airport, National Highway 51, and major expressways including Long Thanh – Dau Giay and Ben Luc – Long Thanh.

PROJECT INFORMATION

Project Name:Oasia SwanBay Villas – Sumi & Miyabi Sub-zones
Location:Dai Phuoc Island, Nhon Trach District, Dong Nai Province
Developer:Dai Phuoc Swancity One Mea
Scale: 342 units including townhouses, shop villas, garden villas, and riverfront villas
Supervision Consultant:Nagecco Construction Consultancy JSC
CFA:185.560 sqm
Land Area:340.000 sqm
Actual images of the Oasia SwanBay Villas – Sumi & Miyabi Sub-zones

As the general contractor, CENTRAL places strong emphasis on engineering solutions tailored to riverfront developments, which are characterized by soft soil conditions, high groundwater levels, and tidal influences. The construction plan has been carefully designed and rigorously controlled by the CENTRAL’s PMB, incorporating ground stabilization techniques, soil reinforcement, and advanced waterproofing solutions for underground structures to ensure long-term structural integrity.

Beyond technical execution, CENTRAL prioritizes strict safety and environmental management standards, while maintaining project progress through optimized resource allocation and shift-based construction planning. This integrated approach reflects the company’s capability to deliver complex projects under challenging site conditions while ensuring quality, safety, and schedule adherence.

Participation in large-scale developments such as Oasia SwanBay continues to reinforce CENTRAL’s position as a leading general contractor in Vietnam, demonstrating the trust placed by investors and strategic partners. Each project contributes to enhancing CENTRAL’s technical expertise, expanding its project portfolio, and advancing its commitment to sustainable development, delivering long-term value to clients, partners, and the broader community.

Overview of the groundbreaking ceremony of the Oasia SwanBay Villas Project
Representatives of all parties take commemorative photos at the groundbreaking ceremony
CEMTRAL’s PMB takes commemorative photos at the groundbreaking ceremony

FAIRMONT HANOI OFFICIALLY OPENS, CENTRAL PROUDLY CONTRIBUTES TO VIETNAM’S FIRST 6-STAR HERITAGE HOTEL IN THE HEART OF OLD QUARTER

In February 2026, Fairmont Hanoi, one of the world’s most prestigious hotel brands with more than a century of heritage, officially announced the opening. Constructed by CENTRAL Construction Joint Stock Company as the main contractor, the project marks the debut of the first 6-star heritage hotel located in the historic Old Quarter of Hanoi, Vietnam.

Fairmont Hotels & Resorts, part of the world  leading hospitality group Accor, is internationally renowned for creating landmark destinations that become deeply rooted in the cities. Since 1907, Fairmont has created magnificent, meaningful and unforgettable hotels, rich with character and deeply connected to the history, culture and community of its destinations. Today, Fairmont operates more than 80 hotels and resorts globally, positioned within the concept of “luxury heritage hospitality” delivering refined experiences that merge historical legacy, local culture, and world-class hospitality.

Rendering of the completed Fairmont Hanoi project – the first 6-star heritage hotel located in the heart of Hanoi’s Old Quarter (Source: Internet).

Fairmont Hanoi represents the culmination of extensive research into Vietnamese culture, history, and art. The project was designed by the internationally acclaimed firms Perkins Eastman and Aston Design, drawing inspiration from the artistry of traditional Vietnamese lacquer painting. Its design language incorporates iconic colors and motifs reflective of Vietnam’s cultural heritage, including the deep red hues symbolizing the Red River’s alluvial soil, French colonial Indochine aesthetics, and decorative patterns inspired by the historical dynasties of Vietnam.

Actual completed images of the Fairmont Hanoi project.

At this landmark development, CENTRAL served as the main construction contractor for the project, which occupies a site of more than 10,000 square meters. The hotel features four basement levels and eight above-ground floors, accommodating 241 guest rooms, including 38 Fairmont Gold rooms, 12 suites, and a Presidential Suite. Given the project’s exceptional prestige and stringent international standards, meticulous planning and disciplined execution were essential throughout the construction process. Among the project’s most technically demanding achievements was the successful completion of a four-level transfer beam floor structure, a complex engineering feat involving massive transfer beams measuring 3 × 2.75 meters, integrated with post-tensioned cables spanning 27 meters within a dramatic 11.45-meter-high atrium space. This solution required advanced engineering capabilities, precise coordination, and rigorous quality control throughout the construction phase.

Construction progress images illustrating the technical solutions implemented to meet the project’s stringent requirements.

Sharing insights on the debut of Vietnam’s first six-star heritage hotel, Mr. Jean-François Brun, General Manager of Fairmont Hanoi, stated:  “We are delighted to indulge our guests in Fairmont’s distinguished hospitality and its premier presence in Hanoi. Fairmont Hanoi joins some of the most storied addresses in the world and we are excited to showcase how we’ve blended our brand’s century-long heritage with the distinctive culture, character, and daily rhythm of Hanoi unfolding around us.”

The opening of Fairmont Hanoi represents a significant milestone in the continued elevation of Vietnam’s luxury tourism and hospitality sector, meeting the rapidly growing demand from high-end travelers. As a key contributor to the project’s construction, CENTRAL takes pride in helping create a landmark development that embodies heritage value and international standards, further affirming its capabilities as one of Vietnam’s leading construction contractors capable of meeting the rigorous technical and quality requirements of the world’s most prestigious hotel brands.

The project also strengthens CENTRAL’s portfolio in the high-end hospitality and resort real estate sector, a strategic segment where the company consistently invests in improving construction quality and technical excellence. Through the application of advanced engineering solutions, innovative material optimization, and modern construction management practices, CENTRAL continues to enhance project efficiency, shorten implementation timelines, and deliver superior building quality-meeting the increasingly demanding expectations of global hospitality brands.

Some other images (source accor.com):

CENTRAL & 620 INFRASTRUCTURE CONTRACTOR JOINT VENTURE LAUNCHES CONSTRUCTION OF THREE MAJOR BRIDGE PROJECTS AT THE START OF LUNAR NEW YEAR 2026

On the first working days of Lunar New Year Binh Ngo 2026, with strong determination and accelerated momentum, the contractor joint venture of Central Construction JSC (CENTRAL) and 620 Infrastructure Development And Investment Corporation officially commenced simultaneous construction of three key infrastructure bridge projects in Ho Chi Minh City and Khanh Hoa Province.

1. Bridge No.1 & Bridge No.2 – Can Gio Sea Reclamation Tourism Urban Area

Project:Bridge No.1 & Bridge No.2 – Can Gio Sea Reclamation Tourism Urban Area
Place:Can Gio Commune, HCMC
Investor:Vinhomes JSC
Scale:Bridge No.1: 680 meters (from Km0+040 to Km0+720)
Bridge No.2: 1,120 meters (from Km0+240 to Km1+360)
Total length:1,800m
Perspective of Bridge No.1 – Can Gio Sea Reclamation Tourism Urban Area
Perspective of Bridge No.2 – Can Gio Sea Reclamation Tourism Urban Area

The Bridge No.1 & Bridge No.2 – Can Gio Sea Reclamation Tourism Urban Area are located along the main axis connecting to the northern T6 route in the Can Thanh area of Can Gio Commune. The main roadway is designed to meet urban arterial street standards, with a design speed of 60 km/h, in compliance with TCVN 13592:2022 and QCVN 07-4:2023/BXD. The primary bridge span measures 390 meters and features a steel arch structure with composite steel deck girders. The bridge is 29 meters wide, comprising four motor vehicle lanes, two mixed-traffic lanes, and two pedestrian sidewalks. Approach bridges utilize precast Super-T prestressed reinforced concrete girders—an optimal technical solution ensuring both construction efficiency and long-term durability.

2. Nguyen Tat Thanh Bridge – Khanh Hoa Province

Project:Nguyen Tat Thanh Bridge
Place:Cam Lam Commune, Khanh Hoa Province
Investor:Vinhomes JSC
Scale:Approximately 400 meters crossing Thuy Trieu Canal along Nguyen Tat Thanh arterial route
Perspective of Nguyen Tat Thanh Bridge

Designed as a modern arch bridge using a combination of steel and reinforced concrete structures, the project includes two independent spans to ensure safe, flexible, and sustainable long-term operation. Nguyen Tat Thanh Bridge is a strategic transportation infrastructure project situated along the key corridor connecting Nha Trang City, Cam Lam District, and Cam Ranh International Airport. The bridge will facilitate mobility, urban expansion, and socio-economic connectivity in southern Khanh Hoa Province.

It is also positioned as a “strategic infrastructure artery,” symbolizing synchronized development between transportation infrastructure and modern urban planning in the Cam Lam – South Khanh Hoa area.

Within its long-term development strategy, CENTRAL has defined four strategic pillars. General Construction remains the core foundation, complemented by three expansion pillars: Infrastructure, International Markets, and Investment.

The infrastructure sector has been prepared well in advance. In 2023, CENTRAL participated in the construction of three bridges along the Can Tho – Hau Giang Expressway. In 2025, CENTRAL acquired a 51% stake in 620 Infrastructure Development And Investment Corporation, marking a pivotal milestone in its strategic expansion into transportation infrastructure development.

The CENTRAL – 620 Infrastructure contractor joint venture forms a strong integrated system combining:

  • CENTRAL’s governance capability, financial strength, and General Contractor expertise
  • 620 Infrastructure’s specialized experience in transportation infrastructure construction

This synergy enables the consortium to proactively manage construction organization, technical control, schedule management, and occupational safety—meeting the stringent requirements of large-scale, high-standard bridge projects.

With a solid operational foundation, a highly qualified engineering team, and a disciplined management system, the CENTRAL – 620 Infrastructure contractor joint venture is committed to delivering projects on schedule, ensuring quality and safety, and contributing to the development of sustainable infrastructure for communities and society at large.

AMBASSADOR OF ISRAEL VISITS AND EXTENDS GREETINGS TO CENTRAL

On February 10th, 2026, H.E. Mr. Yaron Mayer, Ambassador of Israel traveled from Ha Noi to Ho Chi Minh City to visit and meet with the CENTRAL’s BOD and extended New Year greetings and gifts to CENTRAL’s engineers and workers at CENTRAL’s head office. Mr. Tran Quang Tuan, Chairman & CEO of CENTRAL, together with the Company’s BOD, warmly welcomed the Ambassador in a formal, open and cordial atmosphere.

CENTRAL’s BOD welcomed the Ambassador at the head office
H.E. Mr. Yaron Mayer, Ambassador of Israel engaged in friendly discussions and shared valuable insights with CENTRAL’s BOD

On behalf of CENTRAL, the Company’s BOD sincerely thanked the Ambassador for his continued interest, support and companionship. Speaking at the meeting, Chairman & CEO Tran Quang Tuan affirmed: “With a strong sense of responsibility, CENTRAL places great emphasis on carefully evaluating the quality of recruitment and training for Vietnamese engineers, specialists and workers assigned to projects in Israel. We are committed to ensuring proper living conditions, accommodation and a safe, professional working environment for our workforce. At the same time, we look forward to continued support and connection from the Ambassador in promoting cooperation opportunities and project implementation between our two countries.”

Currently, CENTRAL has signed contracts and is directly implementing 8 large-scale projects across several major cities in Israel. The Company has recruited and trained 600 workers, who are ready to be deployed to Israel immediately after the Lunar New Year of the Year of the Horse 2026, enabling the simultaneous execution of multiple projects with a strong spirit of determination.

Greeting Card from H.E. Mr. Yaron Mayer, Ambassador of Israel

At the conclusion of the visit, Chairman & CEO Tran Quang Tuan presented H.E. Mr. Yaron Mayer, Ambassador of Israel with a commemorative gift symbolizing friendship and cooperation. The two sides took souvenir photos, marking a meaningful meeting that opens up promising prospects for practical and sustainable cooperation in the future.

H.E. Mr. Yaron Mayer, Ambassador of Israel and Chairman & CEO Tran Quang Tuan exchange commemorative gifts
H.E. Mr. Yaron Mayer, Ambassador of Israel Mayer takes a commemorative photo with CENTRAL’s BOD

Previously, in May 2025, during an official visit to Viet Nam, Mr. Yoav Ben Tzur, Minister of Labor of the State of Israel, together with Ambassador Yaron Mayer, met with Prime Minister Pham Minh Chinh, leaders of the Ministry of Home Affairs, and representatives of CENTRAL.

The meeting took place in a special context, as no bilateral labor cooperation agreement had yet been signed between the two governments. With the aim of strengthening bilateral relations, H.E. Mr. Yaron Mayer, Ambassador of Israel actively facilitated exchanges between relevant authorities of both countries and advocated for the Vietnamese Government to consider granting a special and unprecedented mechanism allowing CENTRAL to deploy engineers and workers to Israel. 

After nearly 3 years of persistent negotiations and coordination, with close support from the competent authorities of both countries, CENTRAL became the first and only enterprise to be granted a license by the Government of Viet Nam to send workers to Israel (License No. 3191/SNV-VLATLĐ, dated September 11th, 2025). This historic decision not only marks a significant milestone for CENTRAL, but also lays an important foundation for both governments to further evaluate and the labor cooperation framework, opening new opportunities for trade and workforce collaboration between Viet Nam and Israel.

This pioneering milestone provides inspiration and a solid premise for Vietnamese enterprises and workers to confidently participate and operate in the Israeli market in the coming years, while affirming CENTRAL’s credibility, capability and proactive role in international integration.

On the morning of May 21st, 2025, at the Government Office, Israeli Minister of Labor Yoav Ben Tzur met with Prime Minister Pham Minh Chinh

Selected projects currently implemented by CENTRAL in Israel include:

Aura Pivko Project
GS City Project
BS Towers Project